Greenbyte Ideas
Our approach to product feedback
The benefits of giving us your product feedback
What happens to your product feedback
How we choose what to implement
- Customer feedback - there are many ways we listen for your feedback:formal customer interviews and other research activitiesevents like conferences and trade showscomments and votes on issues here in Greenbyte & BluePoint Influence
- CSM team insights - our CSM team knows which issues are the most challenging and most common for customers.
- Product analytics - we track how users move through the system, which helps us understand how existing features are being used.
- Product strategy - our long-term strategic vision for the products.
Custom applications
5 results found
-
Possibility to include curtailments to time-based availability calculations
Would it possible to add a feature that in the time-based availability calculations we would be able to include curtailments in the calculations. Meaning that if a turbine is curtailed to 50% during an hour, the turbine will have availability of 50% during that hour. I assume that this is not anyhow possible at the moment?
14 votesThanks for your feedback, this is a great request. It's open for voting from other users.
-
o Service hours/allowed scheduled maintenance cannot be count into the contractual availability.
Each contract is different and a common detail in a service contract like a maximum allowed number of maintenance hours (not taken into account for the unavailability) is not possible in Greenbyte.
Therefore the numbers in the greenbyte report must be recalculated by the number of scheduled maintenance in order to calculate the contractual availability.2 votesThanks for your feedback, this is a great request. It’s open for voting from other users.
-
Proper calculation of time-base availability when data is missing
As off today, if 10-minutes data are missing for some reason (scada issue for example), then this period is just not taken into account for contractual availability calculation and for system availability calculation. This is an issue because in many case, when accessing the turbines, the maintenance technicians will shut down the communication to prevent remote restart of the turbine, and this loss of communication will also trigger wrong availability calculation.
We expect time-based availability to be based on the period duration, not the 10-min data being there or not, and during data losses, the turbine should be considered available.…9 votes -
Select Availability Category Within Task
When creating a task there is an option that may be selected that is labeled "Affects Downtime". If this option is enabled, the availability contract categories should appear and one should be assigned to the task.
This would be useful for sites that are utilizing tasks to coordinate site work.
8 votes -
Add additional equations for calculating Energetic Availability based on specific OEM contracts
It would be extremely useful to be able to create custom availability contracts that use different methods for calculating lost production and energetic availability.
8 votes